CTS case study - Flexibility

Case Study

On-Site Adjustments During Solar Farm Construction

Delivering 75 MW solar farm with zero change orders & zero liquidated damages.

One of the top 10 EPCs in the United States selected TE Connectivity to provide the Electrical Balance of System (EBoS) for a 75 MW utility-scale solar farm in New Mexico. During construction, engineers encountered an unexpected challenge which could only be resolved thanks to the flexibility and adaptability of TE’s Customizable Trunk Solution CTS.

Project outcome

0

change orders or liquidated damages

12 MW

area reconfigured on-site